Address: 13818 COHASSET ST, VAN NUYS
Overall Job Progress:
Photovoltaic (PV) System <30 kW, Connected to the 4.8 kV System:
Interconnection Application Received | Completed On 02/20/2023 |
Interconnection Application Preliminary Review Started | Completed On 02/21/2023 |
Interconnection Application Preliminary Review Completed | Completed On 02/21/2023 |
ESR Pre-Construction Meeting (Ok to Build) | Completed On 02/21/2023 |
Interconnection Agreement Approved | Bypassed On 02/21/2023 |
Charges Collected | Completed On 02/28/2023 |
ESR Release | Bypassed On 02/21/2023 |
LADBS Release | Completed On 03/09/2023 |
Meter Order Request Sent (Field Order) | Completed On 03/09/2023 |
Meter Installation Assigned to Crew | Completed On 03/10/2023 |
PTO - Permission to Operate System Granted | Completed On 04/20/2023 |
Additional Service Information:
Job Address: 13818 COHASSET ST, VAN NUYS |
Work Request (Work Order) No: 2474214 |
120/240 Volts, 1 Phase, 3 Wire |
Meter Switch Amps: 200 |
Please contact the Connection Center at (213) EMPOWER or (213) 367-6937 if your questions are not answered.