Address: 18241 ARMINTA ST, RESEDA

Overall Job Progress:

100% Complete

Photovoltaic (PV) System <30 kW, Connected to the 4.8 kV System:

Interconnection Application Received Completed On 12/03/2022
Interconnection Application Preliminary Review Started Completed On 12/06/2022
Interconnection Application Preliminary Review Completed Completed On 12/06/2022
ESR Pre-Construction Meeting (Ok to Build) Completed On 12/06/2022
Interconnection Agreement Approved Bypassed On 12/06/2022
Charges Collected Completed On 12/05/2022
ESR Release Bypassed On 12/06/2022
LADBS Release Completed On 02/13/2023
Meter Order Request Sent (Field Order) Completed On 02/13/2023
Meter Installation Assigned to Crew Completed On 02/14/2023
PTO - Permission to Operate System Granted Completed On 03/06/2023


Additional Service Information:

Job Address: 18241 ARMINTA ST, RESEDA
Work Request (Work Order) No: 2440154
120/240 Volts, 1 Phase, 3 Wire
Meter Switch Amps: 200