Address: 14629 GREENLEAF ST, SHERMAN OAKS

Overall Job Progress:

100% Complete

Electric Meter Installation:

Meter Job Created Completed On 09/06/2022
Address Validation Completed On 09/28/2022
ESR Meter Release Completed On 08/24/2023
LADBS Meter Release Completed On 07/31/2023
Received Customer Plans Completed On 09/28/2022
Meter Spot Completed On 10/18/2022
Final Approval (Job Sent to Construction) Completed On 08/24/2023
Job Assigned to Crew Completed On 09/11/2023
Meter Installed Completed On 09/11/2023


Additional Service Information:

Job Address: 14629 GREENLEAF ST, SHERMAN OAKS
Work Request (Work Order) No: 2348294
120/240 Volts, 1 Phase, 3 Wire
Meter Switch Amps: 320
Fault Current: 22,000 Amps AIC