Address: 8947 PETIT AV, NORTH HILLS

Overall Job Progress:

100% Complete

Electric Meter Installation:

Meter Job Created Completed On 08/20/2022
Address Validation Completed On 09/13/2022
ESR Meter Release Bypassed On 09/13/2022
LADBS Meter Release Completed On 05/13/2023
Final Approval (Job Sent to Construction) Completed On 05/13/2023
Job Assigned to Crew Completed On 05/22/2023
Meter Installed Completed On 05/22/2023


Additional Service Information:

Job Address: 8947 PETIT AV, NORTH HILLS
Work Request (Work Order) No: 2341269
120/240 Volts, 1 Phase, 3 Wire
Meter Switch Amps: 200


Please contact the Connection Center at (213) EMPOWER or (213) 367-6937 if your questions are not answered.