Address: 148 W 108TH ST, LOS ANGELES

Overall Job Progress:

100% Complete

Electric Meter Installation:

Meter Job Created Completed On 05/19/2022
Address Validation Completed On 06/13/2023
ESR Meter Release Completed On 06/13/2023
LADBS Meter Release Completed On 06/26/2023
Final Approval (Job Sent to Construction) Completed On 06/26/2023
Job Assigned to Crew Completed On 06/27/2023
Meter Installed Completed On 06/28/2023


Additional Service Information:

Job Address: 148 W 108TH ST, LOS ANGELES
Work Request (Work Order) No: 2299614
Project ID: P302846
120/240 Volts, 1 Phase, 3 Wire
Meter Switch Amps: 100