Address: 5542 FRANRIVERS AV, WOODLAND HILLS

Overall Job Progress:

100% Complete

Electric Meter Installation:

Meter Job Created Completed On 01/12/2022
Address Validation Completed On 07/20/2022
ESR Meter Release Completed On 07/20/2022
LADBS Meter Release Completed On 09/20/2022
Received Customer Plans Completed On 01/12/2022
Meter Spot Completed On 05/07/2022
Final Approval (Job Sent to Construction) Completed On 09/20/2022
Job Assigned to Crew Completed On 09/21/2022
Meter Installed Completed On 10/14/2022


Additional Service Information:

Job Address: 5542 FRANRIVERS AV, WOODLAND HILLS
Work Request (Work Order) No: 2248826
Project ID: P299932
120/240 Volts, 1 Phase, 3 Wire
Meter Switch Amps: 200
Fault Current: 10000 Amps AIC


Please contact the Connection Center at (213) EMPOWER or (213) 367-6937 if your questions are not answered.