Address: 8629 S SEPULVEDA BL, WESTCHESTER
Overall Job Progress:
Electric Meter Installation:
Meter Job Created | Completed On 12/07/2021 |
Address Validation | Completed On 05/05/2023 |
ESR Meter Release | Completed On 05/12/2023 |
LADBS Meter Release | Completed On 02/16/2023 |
Final Approval (Job Sent to Construction) | Completed On 06/20/2023 |
Job Assigned to Crew | Completed On 06/21/2023 |
Meter Installed | Completed On 07/17/2023 |
Additional Service Information:
Job Address: 8629 S SEPULVEDA BL, WESTCHESTER |
Work Request (Work Order) No: 2241035 |
Project ID: P296769 |
120/208 Volts, 3 Phase, 4 Wire |
Meter Switch Amps: 200 |
Fault Current: 47,000 Amps AIC |
Switchboard Info: 1,200 |