Address: 4418 DON DIABLO DR, LOS ANGELES
Overall Job Progress:
Photovoltaic (PV) System <30 kW, Connected to the 4.8 kV System:
Interconnection Application Received | Completed On 07/30/2021 |
Interconnection Application Preliminary Review Started | Completed On 08/24/2021 |
Interconnection Application Preliminary Review Completed | Completed On 08/24/2021 |
Charges Collected | Completed On 08/26/2021 |
ESR Pre-Construction Meeting (Ok to Build) | Completed On 08/24/2021 |
Interconnection Agreement Corrections Sent | Completed On 08/31/2021 |
Interconnection Agreement Approved | Completed On 03/22/2022 |
ESR Release | Bypassed On 01/03/2023 |
LADBS Release | Completed On 03/16/2023 |
Meter Order Request Sent (Field Order) | Completed On 03/16/2023 |
Meter Installation Assigned to Crew | Completed On 03/17/2023 |
PTO - Permission to Operate System Granted | Completed On 04/06/2023 |
Additional Service Information:
Job Address: 4418 DON DIABLO DR, LOS ANGELES |
Work Request (Work Order) No: 2198451 |
120/240 Volts, 1 Phase, 3 Wire |
Meter Switch Amps: 200 |
Please contact the Connection Center at (213) EMPOWER or (213) 367-6937 if your questions are not answered.