Address: 4418 DON DIABLO DR, LOS ANGELES

Overall Job Progress:

100% Complete

Photovoltaic (PV) System <30 kW, Connected to the 4.8 kV System:

Interconnection Application Received Completed On 07/30/2021
Interconnection Application Preliminary Review Started Completed On 08/24/2021
Interconnection Application Preliminary Review Completed Completed On 08/24/2021
Charges Collected Completed On 08/26/2021
ESR Pre-Construction Meeting (Ok to Build) Completed On 08/24/2021
Interconnection Agreement Corrections Sent Completed On 08/31/2021
Interconnection Agreement Approved Completed On 03/22/2022
ESR Release Bypassed On 01/03/2023
LADBS Release Completed On 03/16/2023
Meter Order Request Sent (Field Order) Completed On 03/16/2023
Meter Installation Assigned to Crew Completed On 03/17/2023
PTO - Permission to Operate System Granted Completed On 04/06/2023


Additional Service Information:

Job Address: 4418 DON DIABLO DR, LOS ANGELES
Work Request (Work Order) No: 2198451
120/240 Volts, 1 Phase, 3 Wire
Meter Switch Amps: 200