Address: 535 VISTA GLORIOSA DR, LOS ANGELES

Overall Job Progress:

100% Complete

Electric Meter Installation:

Meter Job Created Completed On 07/19/2021
Address Validation Completed On 08/19/2021
ESR Meter Release Completed On 08/16/2022
LADBS Meter Release Completed On 03/19/2024
Final Approval (Job Sent to Construction) Completed On 03/19/2024
Job Assigned to Crew Completed On 03/20/2024
Meter Installed Completed On 05/06/2024


Additional Service Information:

Job Address: 535 VISTA GLORIOSA DR, LOS ANGELES
Work Request (Work Order) No: 2194716
120/240 Volts, 1 Phase, 3 Wire
Meter Switch Amps: 200
Fault Current: 10,000 Amps AIC
Switchboard Info: 200


Please contact the Connection Center at (213) EMPOWER or (213) 367-6937 if your questions are not answered.