Address: 20120 SHERMAN WY UNIT: 201, WINNETKA

Overall Job Progress:

100% Complete

Electric Meter Installation:

Meter Job Created Completed On 01/28/2021
Address Validation Completed On 02/02/2021
ESR Meter Release Completed On 03/29/2023
LADBS Meter Release Completed On 03/24/2023
Final Approval (Job Sent to Construction) Completed On 03/29/2023
Job Assigned to Crew Completed On 03/30/2023
Meter Installed Completed On 05/02/2023


Additional Service Information:

Job Address: 20120 SHERMAN WY UNIT: 201, WINNETKA
Work Request (Work Order) No: 2138384
Project ID: P287343
120/208 Volts, 1 Phase, 3 Wire
Meter Switch Amps: 100
Fault Current: 60000 Amps AIC
Switchboard Info: NEW 1200A MS2, 208Y/120V, 3PH, 4W


Please contact the Connection Center at (213) EMPOWER or (213) 367-6937 if your questions are not answered.