Address: 1775 BELOIT AV UNIT: HSE, LOS ANGELES

Overall Job Progress:

100% Complete

Electric Meter Installation:

Meter Job Created Completed On 03/21/2019
Address Validation Completed On
Fees Collected Completed On 02/22/2023
ESR Meter Release Completed On 12/29/2022
LADBS Meter Release Completed On 02/06/2023
Final Approval (Job Sent to Construction) Completed On 02/06/2023
Job Assigned to Crew Completed On 02/23/2023
Meter Installed Completed On 03/28/2023


Additional Service Information:

Job Address: 1775 BELOIT AV UNIT: HSE, LOS ANGELES
Work Request (Work Order) No: 1910471
Project ID: P280320
120/208 Volts, 3 Phase, 4 Wire
Meter Switch Amps: 1200
Fault Current: 34000 Amps AIC
Switchboard Info: 1200A PULL SECTION


Please contact the Connection Center at (213) EMPOWER or (213) 367-6937 if your questions are not answered.